Palmetto Parkway - Finishing the job in Aiken County

Schedule

The following sequence dates and durations are preliminary and subject to change. We will be revising this on a periodic basis.

Segment A

  • History - Started Const- 1-2-07; Clearing Complete; Grading Complete; Paving done
  • Forecast - Bridge over Atomic complete – late 2008

Segment B

  • History - Started Const 1-15-07; Clearing Complete; Grading done relocated Radio Station Road opened in early June 07; Bridges at Bradleyville and Power house completed
  • Forecast - Pave in early 09

Segment C

  • History - Started Mid April 07; Clearing Complete; Grading done; Bridge at Clearwater done
  • Forecast - Grading complete in mid 08; start in October 07 Clearwater relocation expected July 08; mainline pave in early 09

Segment D

  • History - Started early March 07; clearing and grading done; Bridge at US 25 Connector complete
  • Forecast - paving complete in late 08

Segment E

  • History - Started early April ’07; Clearing Complete; Grading Complete
  • Forecast - Paving 08- Bridge work on four bridges to be completed late 08

Segment F

  • History - Patching and Paving on I-20 complete; Overlay I-20 with asphalt complete; New ramps complete
  • Forecast - paving spring 09

Segment G

  • History - service roads under construction since July 07
  • Forecast - Completed by end late 08

Segment H

  • History - I-20 ramps under construction as of July 07
  • Forecast - Completed by late 08