Schedule
The following sequence dates and durations are preliminary and subject to change. We will be revising this on a periodic basis.
Segment A
- History - Started Const- 1-2-07; Clearing Complete; Grading Complete; Paving done
- Forecast - Bridge over Atomic complete – late 2008
Segment B
- History - Started Const 1-15-07; Clearing Complete; Grading done relocated Radio Station Road opened in early June 07; Bridges at Bradleyville and Power house completed
- Forecast - Pave in early 09
Segment C
- History - Started Mid April 07; Clearing Complete; Grading done; Bridge at Clearwater done
- Forecast - Grading complete in mid 08; start in October 07 Clearwater relocation expected July 08; mainline pave in early 09
Segment D
- History - Started early March 07; clearing and grading done; Bridge at US 25 Connector complete
- Forecast - paving complete in late 08
Segment E
- History - Started early April ’07; Clearing Complete; Grading Complete
- Forecast - Paving 08- Bridge work on four bridges to be completed late 08
Segment F
- History - Patching and Paving on I-20 complete; Overlay I-20 with asphalt complete; New ramps complete
- Forecast - paving spring 09
Segment G
- History - service roads under construction since July 07
- Forecast - Completed by end late 08
Segment H
- History - I-20 ramps under construction as of July 07
- Forecast - Completed by late 08